Introduction
For high-value projects, like warehouses, manufacturing plants, or commercial facilities, stakeholders want to make sure they get it right the first time to avoid expensive change orders and delays. One tool project managers and owners can use is a third-party review, which offers peace of mind that the project is compliant and designed well.
Third-party reviews are especially valuable when a facility undergoes operational changes, renovations, storage modifications, or system expansions. Owners also commonly request reviews to make sure their fire protection system aligns with the building’s intended use before they spend a lot of money installing the system.
Third-Party Review Overview
A third-party review is an independent evaluation of a building’s designs and/or installation, performed by an expert who is not involved in the project. It’s an objective, external review that looks at systems to verify overall system integrity and soundness.
When should the review take place?
A third-party review can happen at multiple points in a project. The best time to catch problems is early, either during the design criteria stage or during shop drawing review. There can also be field reviews during installation and another review near final inspection.
For existing buildings, a review can happen anytime there is a change in storage, occupancy, tenant, or building use.
For larger or more complicated projects, it can make sense to review at multiple stages:
- Design criteria
- Contractor shop drawings
- During installation
- Final installation
- Later, if the building use or storage changes
Identifying issues during design or shop drawing review is significantly less costly than discovering them after installation, when system components or storage configurations may require modification.
Who Performs the Review?
For fire suppression systems, typically a fire protection engineer or someone with significant sprinkler design and review experience is qualified to perform an independent review. Field experience is also important. Practical field experience is equally important, as installation and coordination challenges are not always apparent through code review alone. It ultimately depends on the type of review.
On projects with complicated systems, such as a large warehouse with fire pumps and high-piled storage, it is important that the reviewer is an expert on NFPA 13, storage protection, early suppression fast response (ESFR), hydraulic calculations, and preferably FM requirements.
Common Issues in the Field
There are many issues that can arise during a project that can be prevented with a thorough third-party review. Some of these issues include
- Design and Classification Issues
- Wrong hazard classification
- Wrong commodity classification
- Incorrect sprinkler criteria
- Hydraulic and Water Supply Concerns
- Incorrect flow test data
- Missed the pressure loss through equipment and devices
- Elevation errors
- Fire pump sizing issues
- Insufficient system capacity
- Storage and Operational Changes
- Storage height changes
- Storage arrangement / packaging
- Commodity changes
- Rack modifications
-
- Installation and Coordination Problems
- Obstructions
- Incorrect sprinkler selection
- Deviations from approved plans
For warehouses especially, one of the biggest problems is that the sprinkler system may have been designed at the start, but the building’s operation changes later. The racks get taller, flue spaces size changes, storage arrangements are modified, different commodities come in, or automation equipment is added. Often, nobody goes back and checks whether the sprinkler system still matches the new conditions.
There can also be schedule impacts if the project fails final inspection or needs to go back through the AHJ. The cost difference between fixing something on paper and fixing it in the field can be significant.
Internal vs Third-Party Review
The biggest difference is independence. Because a third-party reviewer was not involved in the original design or installation, they can evaluate the system from a fresh perspective and assess whether it aligns with the building’s intended use, operational needs, and protection objectives.
A third-party review is not the same as internal reviews that happen over the course of a project. Some examples of internal reviews are below:
- Typically, the sprinkler contractor has its own internal review.
- The engineer of record may also review the shop drawings depending on the project.
- Then the AHJ reviews the sprinkler drawings for permit and code compliance.
The third-party review does not replace the internal reviews that occur by other stakeholders in a project; those serve an important purpose. The issue is that everyone has different responsibilities and motivations. None of the internal reviews require someone to look at the entire sprinkler system specifically from the owner’s risk perspective.
In-House vs. Third-Party: Side-by-Side Comparison
|
Category |
In-House Review |
Third-Party Review |
|
Who performs it |
Sprinkler Contractor, engineer of record, AHJ |
Independent FPE or sprinkler consultant |
|
Independence |
May be involved with the original design or installation |
Independent from the installing contractor |
|
Main purpose |
Complete design, obtain permit, install system |
Independently verify the design and installation |
|
Typical timing |
Normal design and permitting process |
Can happen at design, shop drawing, construction, or final stage |
|
Main focus |
Code compliance and contract requirements |
Code compliance plus design intent and system performance |
|
What it may catch |
Typical design and code issues |
Hydraulic concerns, storage mismatches, wrong sprinkler criteria, field deviations |
|
Scope |
Based on project and permit requirements |
Can be customized based on owner or insurance concerns |
|
Best suited for |
Standard sprinkler projects |
Large warehouses, ESFR, high-piled storage, renovations, existing systems, higher-risk facilities |
Why Owners Choose Independent Reviews
Independent reviews add another layer of quality assurance. They help catch design assumptions, hydraulic limitations, storage protection concerns, and installation discrepancies that may otherwise go unnoticed. For owners, the process offers greater confidence that the completed system will perform as intended and support both compliance and day-to-day operations.
TEC’s Services
Telgian Engineering & Consulting offers third-party review of various fire protection and life safety systems. We can review
- Documents, such as sprinkler drawings, water flow information, storage plans, and previous inspection reports
- Existing systems, like fire pumps and sprinklers
- Design criteria and calculations
- Field installations
- And more
Following our review, our consultants will provide a report identifying the major concerns and recommendations. If the client wants, we can also help coordinate with the contractor, insurance carrier, or AHJ to work through the issues.
Conclusion
Third-party reviews give owners and project teams with an independent look at fire protection system design, installation, and performance. While they do not replace reviews by contractors, engineers of record, or authorities having jurisdiction, they can help identify issues early, before they become costly field modifications. For complex facilities, high-piled storage applications, system renovations, and operational changes, an independent review can provide added confidence that fire protection systems continue to align with both code requirements and how the building is actually used.
Li Li
Li Li is Regional Practice Leader, Fire Protection Engineering, for Telgian Engineering & Consulting (TEC) in Seattle. With more than 12 years of experience in fire protection and sprinkler system design, he leads project execution and supports a wide range of engineering and consulting projects throughout the region. His expertise includes fire sprinkler system design, high-piled storage protection, 3D modeling, BIM coordination, project management, and process improvement. A NICET Level IV-certified professional in Water-Based Systems Layout, Li helps clients develop practical, code-compliant fire protection solutions that align with operational needs and industry standards.
Frequently Asked Questions
What is a third-party fire protection review?
A third-party review is an independent evaluation of a building’s fire protection design, installation, or existing systems. An expert who was not involved in the original project assesses the system’s integrity, code compliance, design intent, and alignment with the building’s actual use.
When should a third-party review take place?
A review can occur during design criteria development, shop drawing review, installation, or final inspection. Existing buildings may also need a review following changes in storage, occupancy, tenants, operations, or building use. Identifying problems during design is typically less costly than correcting installed systems.
How does a third-party review differ from an in-house review?
In-house reviews generally focus on project responsibilities such as completing the design, obtaining permits, meeting contract requirements, and installing the system. A third-party reviewer provides an independent perspective that also considers system performance, operational needs, and the owner’s risk. The third-party review supplements rather than replaces internal and regulatory reviews.
What problems can an independent review identify?
An independent review may uncover incorrect hazard or commodity classifications, unsuitable sprinkler criteria, inaccurate flow-test data, hydraulic calculation errors, inadequate system capacity, fire pump sizing issues, obstructions, installation deviations, and mismatches between the sprinkler system and current storage conditions.
Which projects benefit most from a third-party review?
Third-party reviews are especially useful for large warehouses, manufacturing plants, high-piled storage facilities, renovations, system expansions, existing buildings, and other complex or higher-risk projects. They are also valuable when racks, commodities, packaging, automation equipment, occupancy, or building operations have changed since the system was designed.